IL Application or request received
Received Date: Monday, September 12, 2016
IL Deadline Deadline to request a public hearing
Deadline to Request Public Hearing: Tuesday, September 27, 2016
IL Deadline Public hearing
Public Hearing Date: Friday, November 04, 2016
IL Deadline Public comment deadline
Deadline for Written Comment: Wednesday, January 04, 2017
IL Approved
Project approved 6-0-2 absent at January 24, 2017 Board Meeting
IL Extension issued
Permit renewal approved 5-0 at March 5, 2019 Review Board meeting
IL Permit revoked effective September 30, 2021 required completion date.
IL Denied
Permit Renewal request denied 0-6 at October 26, 2021 State Board meeting