Dates as published by the agency unless marked.
IL Application complete
The application contained a Safety Net Impact Statement and was deemed substantially complete on March 9, 2026.
IL Notice posted
26-012 Touchette Regional Hospital - Establishment
IL Deadline Deadline to request a public hearing
HFSRB staff must receive requests for hearings by March 24, 2026.
IL Deadline Public comment deadline
All public written comments must be received by July 1, 2026.
IL Deadline Staff report expected
HFSRB will post its findings in an HFSRB Staff Report, which will be available via the Internet on July 7, 2026.
IL Deadline Public comment deadline
All written public comments about the HFSRB staff findings must be received before 9:00 am, July 13, 2026.
IL Deadline Board meeting scheduled
Consideration by HFSRB has been tentatively scheduled for the July 21, 2026, meeting.
IL Parser correction (the day DocketTrail detected the change)
raw_status: null -> "Permit Approval Letter"