Kaiser Foundation Health Plan of Washington-HMO Ambulatory Surgical Facility
WA · Latest: WA Approved
State reviews
| State | Agency | Status | Stage | Source |
|---|
| WA | Washington State Department of Health | Approved APPROVED | DECISION | Agency record |
Trail
Dates as published by the agency unless marked.
WA Letter of intent received
Letter of Intent: 03/01/2019 (received)
WA Application or request received
Request: 04/01/2019 (received)
WA Review began
Beginning of Review: 07/16/2019
WA Letter of intent expiry
Letter of Intent: 09/02/2019 (expires)
WA Approved
Evaluation and Decision: 10/25/2019 - project approved
No changes observed since the initial load (WA ).
Parties as filed
Notes
| State | Note as printed | Printed in |
|---|
| WA | Regular review 05/30/19 - Granted applicant's request for a 45-day extension to screening responses. | Parties cell |
Documents (5)
Evidence
One agency record. It is not grouped with any other.
Names as filed and source keys
| State | Title as printed | Source key | Key method |
|---|
| WA | Proposing to add a procedure room to its existing three-procedure room ambulatory surgical facility in Bellevue, within east King County. | CN19-69 | AGENCY_NUMBER |
Observed by DocketTrail
| State | Source key | First seen by DocketTrail (UTC) | Last checked (UTC) | Page checked |
|---|
| WA | CN19-69 | | | doh.wa.gov |