DocketTrail

DaVita, Inc.

WA · Latest: WA Public comment deadline

State reviews

StateAgencyStatusStageSource
WAWashington State Department of HealthApproved APPROVEDDECISIONAgency record

Trail

Dates as published by the agency unless marked.

  1. WA Application or request received
    Request: 09/03/2019 (received)
  2. WA Review began
    Beginning of Review: 02/18/2020
  3. WA Public comment deadline
    End of Public Comment: 03/24/2020

Not dated

  1. WA Approved
    Evaluation and Decision: 05/20/20 - project approved

Changes

Feed

No changes observed since the initial load (WA ).

About the digest

Parties as filed

StateParties as filed
WADaVita, Inc.
Documents (3)
Evidence

One agency record. It is not grouped with any other.

Names as filed and source keys

StateTitle as printedSource keyKey method
WAAmendment to CN19-81, 2019 Cycle 1-Non-Special Circumstances - Proposing to establish a four-station dialysis facility, within King eight.CN19-81AAGENCY_NUMBER

Observed by DocketTrail

StateSource keyFirst seen by DocketTrail (UTC)Last checked (UTC)Page checked
WACN19-81Adoh.wa.gov