  1. WA Letter of intent received
    Letter of Intent: 06/01/2020 (received)
  2. WA Letter of intent expiry
    Letter of Intent: 07/01/2020 (expires)
  3. WA Application or request received
    Request: 07/01/2020 (received)
  4. WA Review began
    Beginning of Review: 12/03/2020
  5. WA Public comment deadline
    End of Public Comment: 01/07/2021
  6. WA Approved
    Evaluation and Decision: 03/04/2021 - project approved

Changes

Feed

No changes observed since the initial load (WA ).

About the digest

Parties as filed

Notes

StateNote as printedPrinted in
WAConverted to regular review 09/10/2020 - Applicant requested and was granted a 45-day extension to respond to screening.Parties cell
Documents (5)
Evidence

One agency record. It is not grouped with any other.

Names as filed and source keys

StateTitle as printedSource keyKey method
WA2020 concurrent review, cycle one, nonspecial circumstances, proposing to relocate part of an existing dialysis facility, within the Thurston County ESRD Planning Area.CN21-04AGENCY_NUMBER