  1. WA Letter of intent received
    Letter of Intent: 05/01/2023 (received)
  2. WA Letter of intent expiry
    Letter of Intent: 06/01/2023 (expires)
  3. WA Application or request received
    Request: 06/01/2023 (received)
  4. WA Review began
    Beginning of Review: 11/07/2023
  5. WA Public comment deadline
    End of Public Comment: 12/12/2023
  6. WA Approved
    Evaluation and Decision: 02/12/2024 - project approved

Changes

Feed

No changes observed since the initial load (WA ).

About the digest

Parties as filed

StateParties as filed
WADaVita
Documents (5)
Evidence

One agency record. It is not grouped with any other.

Names as filed and source keys

StateTitle as printedSource keyKey method
WALetter of Intent submitted on 5.1.2023 to relocate and expand DaVita Mid Columbia kidney center by seven CN-approved stations in Franklin County. Capital Expenditure $4,089,787.CN23-36AGENCY_NUMBER

Observed by DocketTrail

StateSource keyFirst seen by DocketTrail (UTC)Last checked (UTC)Page checked
WACN23-36doh.wa.gov