Total Renal Care, Inc. (dba DaVita Federal Way)
WA · Latest: WA Approved
State reviews
| State | Agency | Status | Stage | Source |
|---|
| WA | Washington State Department of Health | Approved APPROVED | DECISION | Agency record |
Trail
Dates as published by the agency unless marked.
WA Letter of intent received
Letter of Intent: 10/31/2024 (received)
WA Application or request received
Request: 12/02/2024 (received)
WA Review began
Beginning of Review: 02/17/2025
WA Public comment deadline
End of Public Comment: 03/24/2025
WA Letter of intent expiry
Letter of Intent: 04/30/2025 (expires)
WA Approved
Evaluation and Decision: 5/21/2025 - project approved
No changes observed since the initial load (WA ).
Parties as filed
Notes
| State | Note as printed | Printed in |
|---|
| WA | CN2025 issued 05/23/2025 | Parties cell |
Documents (5)
Evidence
One agency record. It is not grouped with any other.
Names as filed and source keys
| State | Title as printed | Source key | Key method |
|---|
| WA | Proposing to expand DaVita Federal Way Community Dialysis Center by five (5) stations. | CN25-12 | AGENCY_NUMBER |
Observed by DocketTrail
| State | Source key | First seen by DocketTrail (UTC) | Last checked (UTC) | Page checked |
|---|
| WA | CN25-12 | | | doh.wa.gov |